Schedule

Announced and approvedJun 2, 2017
20182019
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Prince Albert
Construction start
Apr 3, 2018(actual)
Construction end
Aug 12, 2019(actual)