New River Street Water Reservoir
Federal contribution
$6.0M
$6,000,000
Federal share50%
of $12.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
20182019
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Prince Albert
- Construction start
- Apr 3, 2018(actual)
- Construction end
- Aug 12, 2019(actual)
Also in Prince Albert
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49995 in the federal list. How to read these figures.