WTP & SPS #2,3,4 Upgrades & Portable Generator Purchase - Northern
Federal contribution
$1.7M
$1,699,998
Federal share33%
of $5.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 20, 2009
200920102011201220132014
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Northern Village of Buffalo Narrows
- Construction start
- Aug 12, 2012(actual)
- Construction end
- Apr 14, 2014(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jul 3, 2012
- Construction end12 months earlyforecast Mar 31, 2015
Also in Prince Albert
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23152 in the federal list. How to read these figures.