Back to projects

Charlottetown Pollution Control Plant Upgrades

Charlottetown, Prince Edward Island

completeWastewaterCWWF
Federal contribution
$6.3M
$6,325,000
Federal share50%

of $12.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2017
2018201920202021
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Charlottetown
Construction start
May 1, 2017(actual)
Construction end
Dec 31, 2020(actual)

Against the original forecast

  • Construction start19 months earlyforecast Dec 11, 2018
  • Construction end9 months lateforecast Mar 31, 2020

Also in Charlottetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49540 in the federal list. How to read these figures.