Charlottetown Pollution Control Plant Upgrades
Charlottetown, Prince Edward Island
Federal contribution
$6.3M
$6,325,000
Federal share50%
of $12.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2017
2018201920202021
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Charlottetown
- Construction start
- May 1, 2017(actual)
- Construction end
- Dec 31, 2020(actual)
Against the original forecast
- Construction start19 months earlyforecast Dec 11, 2018
- Construction end9 months lateforecast Mar 31, 2020
Also in Charlottetown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49540 in the federal list. How to read these figures.