Federal contribution
$25.0M
$25,000,000
Federal share41%

of $61.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 13, 2024
today
2024202520262027
BuiltForecast

Approved 5 weeks before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Sep 15, 2024(actual)
Construction end
Sep 30, 2027(forecast)