Charlottetown Library Learning Centre
Charlottetown, Prince Edward Island
Federal contribution
$6.3M
$6,343,400
Federal share40%
of $15.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 21, 2019
202020212022
Built
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Charlottetown Area Development Corporation
- Construction start
- May 11, 2020(actual)
- Construction end
- Jul 12, 2022(actual)
Against the original forecast
- Construction start5 months lateforecast Dec 16, 2019
- Construction end4 months earlyforecast Oct 31, 2022
Also in Charlottetown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54388 in the federal list. How to read these figures.