Waste Pollution Control Facility Upgrades - Phase 1 - LRAR
Federal contribution
$5.9M
$5,886,054
Federal share20%
of $28.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
201820192020
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Portage La Prairie
- Construction start
- Mar 12, 2018(actual)
- Construction end
- May 28, 2020(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Apr 1, 2018
- Construction end8 weeks lateforecast Mar 31, 2020