Portage La Prairie Regional Recreation Muliplex
Federal contribution
$3.3M
$3,333,333
Federal share9%
of $35.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 18, 2008
200920102011
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Portage la Prairie
- Construction start
- Sep 8, 2008(actual)
- Construction end
- Aug 24, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 30, 2008
- Construction end2.1 years lateforecast Jun 30, 2009
Also in Portage la Prairie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18415 in the federal list. How to read these figures.