CLRUSC Regional Water Supply System Extension
Federal contribution
$32.4M
$32,443,200
Federal share50%
of $64.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2016
20172018201920202021
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Bonnyville
- Construction start
- Nov 15, 2018(actual)
- Construction end
- Jan 31, 2021(actual)
Against the original forecast
- Construction start6 weeks lateforecast Oct 1, 2018
Also in Bonnyville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47574 in the federal list. How to read these figures.