Bonnyville, Alberta

completeRecreationMRIF
Federal contribution
$2.1M
$2,138,481
Federal share32%

of $6.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 13, 2007
2007200820092010
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Bonnyville
Construction start
Jan 23, 2007(actual)
Construction end
Sep 30, 2010(actual)

Against the original forecast

  • Construction start2 months earlyforecast Apr 1, 2007
  • Construction end6 months lateforecast Mar 31, 2010