45th Avenue Rehabilitation
Federal contribution
$890,046
Federal share26%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Bonnyville
- Construction start
- Sep 21, 2009(actual)
- Construction end
- Dec 21, 2010(actual)
Against the original forecast
- Construction start3 months lateforecast Jul 1, 2009
- Construction end10 months earlyforecast Oct 31, 2011