Resurfacing Highway 659
Federal contribution
$1.4M
$1,416,667
Federal share47%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Jun 1, 2010(actual)
- Construction end
- Jun 15, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2010
- Construction end4 months earlyforecast Oct 15, 2011
Also in Bonnyville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28701 in the federal list. How to read these figures.