Robert O. Picard Environmental Center Thickening and Dewatering Building Heating, Ventilation and Air Conditioning Upgrade

Ottawa, Ontario

completeWastewaterCWWF
Federal contribution
$9.9M
$9,925,000
Federal share50%

of $19.9M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 23, 2017
ApprovedMar 27, 2018
20172018201920202021
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Ottawa
Construction start
Jan 3, 2017(actual)
Construction end
Nov 30, 2020(actual)

Against the original forecast

  • Construction start9 months lateforecast Apr 1, 2016
  • Construction end10 months earlyforecast Sep 30, 2021

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49200 in the federal list. How to read these figures.