Ottawa Light Rail Transit (LRT) Stage 2
Federal contribution
$1.1B
$1,091,150,000
Federal share31%
of $3.5B total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 16, 2017
today
20182020202220242026
BuiltForecast
Approved 3 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- City of Ottawa
- Construction start
- Jul 2, 2019(actual)
- Construction end
- Nov 6, 2026(forecast)
Also in Ottawa