Ottawa Combined Sewage Storage Tunnel

Ottawa, Ontario

completeWastewaterNRP
Federal contribution
$62.1M
$62,090,000
Federal share33%

of $189.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 7, 2015
20162017201820192020
Built

Approved 2 weeks after the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
City of Ottawa
Construction start
Aug 11, 2016(actual)
Construction end
Aug 28, 2020(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2016
  • Construction end12 months earlyforecast Aug 31, 2021