Ottawa Combined Sewage Storage Tunnel
Federal contribution
$62.1M
$62,090,000
Federal share33%
of $189.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 7, 2015
20162017201820192020
Built
Approved 2 weeks after the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- City of Ottawa
- Construction start
- Aug 11, 2016(actual)
- Construction end
- Aug 28, 2020(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2016
- Construction end12 months earlyforecast Aug 31, 2021