LRT Stage 2 - Early works and preliminary engineering

Ottawa, Ontario

completePublic TransitPTIF
Federal contribution
$45.0M
$45,000,000
Federal share50%

of $90.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedJul 10, 2017
201720182019
Built

Approved 11 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Ottawa
Construction start
Apr 1, 2016(actual)
Construction end
Feb 28, 2019(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Mar 31, 2019

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47454 in the federal list. How to read these figures.