Village of Rockyford - Wheatland Regional - Phase 2 - WTP Upgrade/Waterline to Rockyford
Federal contribution
$8.2M
$8,153,712
Federal share45%
of $17.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Rockyford
- Construction start
- May 25, 2016(actual)
- Construction end
- Mar 31, 2019(actual)
Against the original forecast
- Construction start5 months earlyforecast Nov 1, 2016
Also in Rockyford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47604 in the federal list. How to read these figures.