Sewer Outfall Replacement

Inuvik, Northwest Territories

completeWastewaterCWWF
Federal contribution
$7.5M
$7,500,000
Federal share75%

of $10.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 6, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Inuvik
Construction start
May 1, 2017(actual)
Construction end
Mar 13, 2020(actual)

Against the original forecast

  • Construction end3 weeks earlyforecast Mar 31, 2020