Inuvik Wind Generation

Inuvik, Northwest Territories

completeGreen EnergyAEF
Federal contribution
$30.0M
$30,000,000
Federal share75%

of $40.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 13, 2018
201920202021202220232024
Built

Approved 8 weeks before the announcement.

Program
Arctic Energy Fund
Ultimate recipient
NT Energy
Construction start
Feb 1, 2022(actual)
Construction end
Oct 31, 2023(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Dec 10, 2021
  • Construction end11 months earlyforecast Sep 30, 2024

Also in Inuvik