Highway 8 Reconstruction
Federal contribution
$18.0M
$18,000,000
Federal share100%
of $18.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 22, 2024
today
20252026202720282029
BuiltForecast
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Government of Northwest Territories
- Construction start
- Sep 10, 2025(actual)
- Construction end
- Mar 31, 2029(forecast)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2025
Also in Inuvik
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 122032 in the federal list. How to read these figures.