MSC Solar and Battery Storage
Federal contribution
$5.6M
$5,556,556
Federal share100%
of $5.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 27, 2022
today
2023202420252026
BuiltForecast
Approved 2 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Town of Inuvik
- Construction start
- Jul 15, 2024(actual)
- Construction end
- Sep 30, 2026(forecast)
Against the original forecast
- Construction start2 months lateforecast May 1, 2024
Also in Inuvik