Town of Inuvik Utilidor Replacement
Federal contribution
$4.3M
$4,297,000
Federal share75%
of $5.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2016
2016201820202022
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Inuvik
- Construction start
- Jun 1, 2016(actual)
- Construction end
- Nov 30, 2021(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 1, 2016
- Construction end9 months earlyforecast Sep 1, 2022
Also in Inuvik