Town of Inuvik Utilidor Replacement

Inuvik, Northwest Territories

completeWastewaterSCF
Federal contribution
$4.3M
$4,297,000
Federal share75%

of $5.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2016
2016201820202022
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Inuvik
Construction start
Jun 1, 2016(actual)
Construction end
Nov 30, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2016
  • Construction end9 months earlyforecast Sep 1, 2022

Also in Inuvik

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46609 in the federal list. How to read these figures.