Rehabilitation of the York-Durham Sewer on 16th Avenue the City of Markham
Federal contribution
$12.1M
$12,145,500
Federal share50%
of $24.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2017201920212023
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional Municipality of York
- Construction start
- Apr 2, 2017(actual)
- Construction end
- Aug 31, 2023(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 15, 2016
- Construction end7 months earlyforecast Mar 31, 2024
Also in York
- Regional Municipality of York - Transit Fleet Electrification$76.0M
- York Durham Sewage System Forcemain Twinning$43.3M
- Yonge North Subway Extension - Planning and Preliminary Engineering$36.3M
- Groundwater Supply System Improvements to Mitigate Impacts of Extreme Weather Events on Lake Based Supplies$18.1M
- Sherman Campus$10.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48980 in the federal list. How to read these figures.