York Durham Sewage System Forcemain Twinning

York, Ontario

completeDisaster MitigationDMAF
Federal contribution
$43.3M
$43,285,341
Federal share36%

of $120.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 26, 2019
202020212022
Built
Program
Disaster Mitigation and Adaptation Fund
Construction start
Jun 10, 2019(actual)
Construction end
Nov 30, 2021(actual)

Against the original forecast

  • Construction end6 months earlyforecast May 31, 2022

Also in York

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52907 in the federal list. How to read these figures.