Groundwater Supply System Improvements to Mitigate Impacts of Extreme Weather Events on Lake Based Supplies

York, Ontario

underwayDisaster MitigationDMAF
Federal contribution
$18.1M
$18,107,200
Federal share40%

of $45.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 9, 2020
today
20212024202720302033
BuiltForecast

Approved 4 weeks before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Construction start
Jun 1, 2025(actual)
Construction end
Mar 31, 2033(forecast)

Against the original forecast

  • Construction start21 months lateforecast Sep 1, 2023

Also in York

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52910 in the federal list. How to read these figures.