Sherman Campus
Federal contribution
$10.2M
$10,168,095
Federal share38%
of $27.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 30, 2016
20172018201920202021
Built
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Jewish Community Properties of Greater Toronto
- Construction start
- Nov 13, 2017(actual)
- Construction end
- Oct 30, 2020(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2017
- Construction end7 months lateforecast Mar 30, 2020
Also in York
- Regional Municipality of York - Transit Fleet Electrification$76.0M
- York Durham Sewage System Forcemain Twinning$43.3M
- Yonge North Subway Extension - Planning and Preliminary Engineering$36.3M
- Groundwater Supply System Improvements to Mitigate Impacts of Extreme Weather Events on Lake Based Supplies$18.1M
- Rehabilitation of the York-Durham Sewer on 16th Avenue the City of Markham$12.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46739 in the federal list. How to read these figures.