Regional Municipality of York - Transit Fleet Electrification

York, Ontario

underwayPublic TransitZETF
Federal contribution
$76.0M
$76,000,000
Federal share18%

of $424.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 5, 2024
today
202320242025202620272028
BuiltForecast

Approved 19 months before the announcement.

Program
Zero Emission Transit Fund
Construction start
Nov 24, 2024(actual)
Construction end
Mar 31, 2028(forecast)

Against the original forecast

  • Construction start23 months lateforecast Jan 1, 2023

Also in York

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65155 in the federal list. How to read these figures.