North Red Deer Regional Wastewater Commission - Wastewater Transmission Line - Lacombe/Blackfalds to Red Deer Wastewater Treatment Plant

Lacombe, Alberta

completeWastewaterCWWF
Federal contribution
$29.9M
$29,881,672
Federal share50%

of $59.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
May 7, 2016(actual)
Construction end
Feb 28, 2019(actual)

Against the original forecast

  • Construction start6 months earlyforecast Nov 1, 2016
  • Construction end3 months lateforecast Nov 30, 2018

Also in Lacombe

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47598 in the federal list. How to read these figures.