Resurfacing Highway 815
Federal contribution
$572,203
Federal share50%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Apr 19, 2010(actual)
- Construction end
- Jun 8, 2010(actual)
Against the original forecast
- Construction end10 months earlyforecast Mar 31, 2011
Also in Lacombe
- North Red Deer Regional Wastewater Commission - Wastewater Transmission Line - Lacombe/Blackfalds to Red Deer Wastewater Treatment Plant$29.9M
- Lacombe Regional Centennial Centre$938.0K
- Aspelund Road Overlay$703.2K
- Sylvan Lake- Lake Side Developments Sanitary Servicing$639.0K
- Highway 12 - Canadian National Railway Overpass on Highway 12 at Alix$226.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28719 in the federal list. How to read these figures.