Rehabilitation of Pickering Bridges
Federal contribution
$199,305
Federal share33%
of $597.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
200620072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Pickering
- Construction start
- May 31, 2005(actual)
- Construction end
- Feb 11, 2008(actual)
Against the original forecast
- Construction end13 months lateforecast Dec 31, 2006