Back to projects

Rosebank Road Sanitary Sewerage Pumping Station

Pickering, Ontario

completeWastewaterISF
Federal contribution
$1.8M
$1,758,811
Federal share32%

of $5.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jun 2, 2010(actual)
Construction end
Oct 31, 2011(actual)

Also in Pickering