Reconstruction of the Abbot Crescent Stormwater Management Pond in the City of Pickering to improve water quantity, quality and erosion control to Ganatsekiagon Creek
Federal contribution
$450,000
Federal share50%
of $900.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
20182019
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Pickering
- Construction start
- Sep 15, 2017(actual)
- Construction end
- Dec 31, 2018(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 3, 2017
- Construction end15 months earlyforecast Mar 31, 2020