Reconstruction of Pinegrove/Hwy 17 Link

Arnprior, Ontario

completeHighways and RoadsMRIF
Federal contribution
$186,683
Federal share33%

of $560.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
2006
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of McNab/Braeside
Construction start
Apr 20, 2005(actual)
Construction end
Oct 2, 2006(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 15, 2004
  • Construction end7 months lateforecast Feb 20, 2006

Also in Arnprior

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11808 in the federal list. How to read these figures.