Replacement of Sandhill Road Culvert

Sundridge, Ontario

completeHighways and RoadsMRIF
Federal contribution
$58,434
Federal share33%

of $175.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
200620072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Joly
Construction start
Apr 20, 2005(actual)
Construction end
Mar 18, 2008(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Mar 1, 2005
  • Construction end21 months lateforecast Jun 30, 2006

Also in Sundridge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11884 in the federal list. How to read these figures.