Back to projects

Replacement of Bridges # 8, 20, 28 and 29

Orangeville, Ontario

completeHighways and RoadsMRIF
Federal contribution
$497,158
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
20062007200820092010
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Mono
Construction start
Apr 20, 2005(actual)
Construction end
Jan 27, 2010(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 1, 2005
  • Construction end2.1 years lateforecast Dec 31, 2007

Also in Orangeville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11897 in the federal list. How to read these figures.