Replacement of River Road Bridge
Federal contribution
$132,000
Federal share33%
of $396.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
20062007
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Magnetawan
- Construction start
- Jun 1, 2005(actual)
- Construction end
- Jan 30, 2007(actual)
Against the original forecast
- Construction end3 months lateforecast Oct 31, 2006
Also in Magnetawan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11918 in the federal list. How to read these figures.