Rehabilitiation of Ahmick Lake Road
Federal contribution
$210,000
Federal share33%
of $630.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Magnetawan
- Construction start
- Nov 25, 2009(actual)
- Construction end
- Oct 19, 2010(actual)
Against the original forecast
- Construction start5 months lateforecast Jun 22, 2009
- Construction end7 weeks lateforecast Sep 1, 2010
Also in Magnetawan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32690 in the federal list. How to read these figures.