Replacement of Goodfellow Road Bridge
Federal contribution
$133,750
Federal share33%
of $401.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
2006
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Brighton
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Jul 13, 2006(actual)
Against the original forecast
- Construction start4 months lateforecast Dec 15, 2004
- Construction end6 months lateforecast Jan 15, 2006
Also in Brighton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11947 in the federal list. How to read these figures.