Back to projects

Pickleball Court Infrastructure

Brighton, Ontario

completeActive TransportationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
2022
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Municipality of Brighton
Construction start
Nov 1, 2021(actual)
Construction end
Jul 31, 2022(actual)

Also in Brighton