Replacement of the Spencerville Bridge
Federal contribution
$355,333
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
200620072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- United Counties of Leeds & Grenville
- Construction start
- May 1, 2005(actual)
- Construction end
- Apr 22, 2008(actual)
Against the original forecast
- Construction end16 months lateforecast Dec 31, 2006
Also in Brockville
- Brockville Water Pollution Control Centre Upgrade$22.3M
- Construction of the Maritime Discovery Centre of the 1000 Islands (MDC)$5.7M
- HVAC, Bottle Water Filling Station, Portable, Retrofits, Wifi, Windows$5.2M
- Automatic Door Opener; Video Camera Childcare Project Group; Washroom Project Group; Site Project Group; HVAC Ventilation Upgrades$2.1M
- To replace aging HVAC Equipment and Controls.$2.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12005 in the federal list. How to read these figures.