Federal contribution
$355,333
Federal share33%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
200620072008
Built
Program
Municipal Rural Infrastructure Fund
Construction start
May 1, 2005(actual)
Construction end
Apr 22, 2008(actual)

Against the original forecast

  • Construction end16 months lateforecast Dec 31, 2006

Also in Brockville