Brockville Water Pollution Control Centre Upgrade

Brockville, Ontario

completeWastewaterCSIF
Federal contribution
$22.3M
$22,311,148
Federal share49%

of $46.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 5, 2007
20082009201020112012
Built

Approved 3 weeks before the announcement.

Program
Canada Strategic Infrastructure Fund
Construction start
Feb 25, 2010(actual)
Construction end
Aug 14, 2012(actual)

Against the original forecast

  • Construction end2.6 years earlyforecast Mar 31, 2015

Also in Brockville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44511 in the federal list. How to read these figures.