Rehabilitation of the Perth Street Elevated Water Storage Tower

Brockville, Ontario

completeDrinking WaterGIS
Federal contribution
$963,600
Federal share40%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
202320242025
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Brockville
Construction start
Apr 21, 2025(actual)
Construction end
Nov 7, 2025(actual)

Against the original forecast

  • Construction end8 weeks earlyforecast Dec 31, 2025