Water System Improvements

Clair, New Brunswick

completeDrinking WaterMRIF
Federal contribution
$957,141
Federal share33%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 31, 2005
2006200820102012
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Clair
Construction start
Oct 18, 2005(actual)
Construction end
Dec 21, 2012(actual)

Against the original forecast

  • Construction start6 months earlyforecast May 1, 2006
  • Construction end3.1 years lateforecast Nov 26, 2009

Also in Clair

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12078 in the federal list. How to read these figures.