Water System Improvements
Federal contribution
$957,141
Federal share33%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 31, 2005
2006200820102012
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Clair
- Construction start
- Oct 18, 2005(actual)
- Construction end
- Dec 21, 2012(actual)
Against the original forecast
- Construction start6 months earlyforecast May 1, 2006
- Construction end3.1 years lateforecast Nov 26, 2009
Also in Clair
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12078 in the federal list. How to read these figures.