Improvements to sewer system and wastewater treatment system
Federal contribution
$642,366
Federal share33%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2009
20102011
Built
Approved 2 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Village of Clair
- Construction start
- Sep 27, 2010(actual)
- Construction end
- Oct 14, 2011(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 1, 2010
- Construction end2 weeks lateforecast Sep 30, 2011