Back to projects

Improvements to sewer system and wastewater treatment system

Clair, New Brunswick

completeWastewaterCC Top Up
Federal contribution
$642,366
Federal share33%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2009
20102011
Built

Approved 2 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Village of Clair
Construction start
Sep 27, 2010(actual)
Construction end
Oct 14, 2011(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2010
  • Construction end2 weeks lateforecast Sep 30, 2011