Upgrading the Nipigon Sewage Treatment Plant to a Secondary Treatment Process
Federal contribution
$341,938
Federal share45%
of $759.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
2006200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Nipigon
- Construction start
- Jan 1, 2006(actual)
- Construction end
- Oct 23, 2009(actual)
Against the original forecast
- Construction start4 months lateforecast Sep 1, 2005
- Construction end24 months lateforecast Oct 31, 2007
Also in Nipigon
- Nipigon Wastewater Treatment$3.5M
- Churchill St. Linear Infrastructure Renewal$268.3K
- Nipigon Recreation Swimming Pool, Nipigon Community Centre Heating and Ventilation System$187.0K
- Restoration of existing storm sewer collection system, manhole, catch basins and storm sewer pipe.$104.2K
- Township of Nipigon Public Works Garage Renovation$80.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12085 in the federal list. How to read these figures.