Churchill St. Linear Infrastructure Renewal

Nipigon, Ontario

completeDrinking WaterSCF
Federal contribution
$268,306
Federal share33%

of $805.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 14, 2015
20162017
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Township of Nipigon
Construction start
Jun 15, 2016(actual)
Construction end
Dec 30, 2016(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 16, 2016
  • Construction end6 weeks lateforecast Nov 20, 2016