Whatì Access Road - Improvements
Federal contribution
$15.0M
$15,000,000
Federal share100%
of $15.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 22, 2024
20242025
Built
Approved 10 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Government of Northwest Territories
- Construction start
- May 20, 2024(actual)
- Construction end
- Jun 9, 2025(actual)
Against the original forecast
- Construction end13 months earlyforecast Jun 30, 2026
Also in Whatì
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 121172 in the federal list. How to read these figures.