Sewage Lagoon Upgrade

Whatì, Northwest Territories

completeWastewaterCWWF
Federal contribution
$375,000
Federal share75%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 6, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Construction start
Jul 1, 2018(actual)
Construction end
Mar 2, 2020(actual)

Against the original forecast

  • Construction start13 months lateforecast Jun 1, 2017
  • Construction end4 weeks earlyforecast Mar 31, 2020