Maple Creek Drainage Pump Station - Intake # 2

Port Coquitlam, British Columbia

underwayDisaster MitigationDMAF
Federal contribution
$5.6M
$5,600,000
Federal share40%

of $14.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2024
today
202520262027
BuiltForecast

Approved 7 months before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Ultimate recipient
City of Port Coquitlam
Construction start
Jul 15, 2025(actual)
Construction end
Jun 11, 2027(forecast)

Also in Port Coquitlam

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 121258 in the federal list. How to read these figures.