Port Coquitlam Recreation Centre
Port Coquitlam, British Columbia
Federal contribution
$12.5M
$12,500,000
Federal share11%
of $117.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 29, 2015
ApprovedApr 5, 2016
201620172018201920202021
Built
Approved 8 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- City of Port Coquitlam
- Construction start
- Apr 17, 2017(actual)
- Construction end
- Jul 13, 2021(actual)
Against the original forecast
- Construction end4 months earlyforecast Oct 29, 2021