Purchase of vehicles and supporting infrastructure to expand community transit solutions in Creighton, Flin Flon, Denare Beach, and neighboring Indigenous communities in Northern Saskatchewan.

Creighton, Saskatchewan

completePublic TransitRTSF
Federal contribution
$242,803
Federal share80%

of $303.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 27, 2024
202420252026
Built

Approved 8 months before the announcement.

Program
Permanent Public Transit Program
Ultimate recipient
Northern Town of Creighton
Construction start
Sep 30, 2023(actual)
Construction end
Feb 26, 2026(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Nov 1, 2023
  • Construction end5 months lateforecast Oct 1, 2025

Also in Creighton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 121697 in the federal list. How to read these figures.